Surface where Wolmix
should be structurally
sound, free from dust,
dirt, oil and substances
reducing adhesion. Paint
on the surface should be
completely removed.
Major defects sould be
repaired by Wolmix prior
to final leveling. 6-7
kg clean water is
gradually added to 25 kg
Wolmix It is throughly
mixed by low speed mixer
(preferably 400 rpm)
until required
consistency. It takes
5-10 minutes to becomes
paste consistency. Mixed
again and paste becomes
ready to apply. Wolmix
is applied by special
spade or steel trowell.
First layer is applied,
if required second layer.
In hot and dry weather
surfaces should be
wetted to allow
hydration. Mortar should
be consumed with in
following 3 hours.
Mortar should not be
used after hardening.
Times given above ar
efor 23˚C and 50%
relative humidity in hot
and dry seasons surface
to be applied should be
wetted. Leveled sufaces
should not be subject to
external effect until
setting. İnitial set of
paste takes 1 week.
Final set takes 28 days.
When required glasswool
mesh may be used for
major cracks. |